Scott Kriston attended the TXDOT FM 2499 phase 4 weekly project meeting this week. The TXDOT FM 2499 project status is as follows: The project is 35% complete as of March 31st. The contractor is finishing the installation of the pillar cross members for the proposed bridge at the Hickory Creek Branch of Lake Lewisville. Bridge beams are delivered and installed on the southern end of the Poindexter branch bridge. The bridge beams for the northern part of the Poindexter bridge are delivered. Bridge decking will start to be constructed on the Poindexter bridge next week. The contractor is installing retaining walls along the entire project. Harlington Drive and Saddlebrook Drive access will be closed to traffic for a 3 month period so they can construct the south bound lanes of FM 2499. The contractor has milled the old asphalt roadway and is cutting the new grade of FM 2499. KCS Railroad has delivered the materials for the new railroad crossing on FM 2499. The railroad contractor will have TX DOT close FM 2499 on May 5th & 6th to install the new crossing. The TXDOT contractor has installed the asphalt base for the northbound and southbound lanes from Highland Shores Boulevard north to approximately 1000 feet south of the Northwood / Castlewood intersection. Steel has been laid out & tied in the southbound lanes, concrete pavement will be poured within the next few weeks.
PUBLIC SAFETY (POLICE AND FIRE)
Fire:
Police:
Auxiliary Lieutenant Steve Jones, Bronze Award, 198 hrs.
Auxiliary Deputy Commander Dick Williams, Bronze Award, 191 hrs.
Auxiliary Chandra Artham, Bronze Award, 104 hrs.
Auxiliary Mike McCoy, Bronze Award, 103 hrs.
Auxiliary Jay Myers, Bronze Award, 101 hrs.
STREET / UTILITY DIVISIONS PROJECTS
Scott Kriston attended the UTRWD 60-inch water line monthly progress meeting this week. The project status is as follows: The project is 38% complete as of March 31st. The tunnel contractor completed the FM407 tunnel and has moved to the west side of the project near Barnett Blvd. The 60-inch water pipe is scheduled to be delivered in 2-weeks and the open cut installation will begin on the eastern portion of the project.
Scott Kriston performed a final walk through on the Highland Oaks Subdivision this week. The contractor is working on the punch list that was created.
Scott Kriston met with BW2 Engineers this week to discuss the Hillside Dr. Paving & Drainage Improvements project, phase 1 of the storm sewer system inspection project and the 2009 asphalt rehabilitation project.
Utility Crews:
Drainage crews:
PARKS DEPARTMENT
On Monday night, BW2 Engineers and Parks' staff held a public forum at the Park Board/Inland Trail Steering Committee meeting to discuss Copperas Trail and Castlewood Trail construction.
All crews are involved in weekly mowing cycles.
Staff at Copperas Park repaired and installed a gate accessing Corps property near the park.
Wes Nienhuser worked on spreading and removing fill dirt from a parking area near the Unity Park soccer fields.
Tommy White met with an electrical contractor this week concerning upgrading several campsites at Pilot Knoll Park from 30 amps to 50 amps capacity in the near future.
On Saturday, Parks staff will host a Spring Clean Up at Copperas Park from 8:30 a.m. to 2:30 p.m. We will be accepting household hazardous waste, e-waste, brush and limb waste and also document shredding.
Senior All Stars:
The Highland Village Senior All Stars met on Monday (27 attendees) and Thursday (28 attendees) at the Highland Shores Community Center for game day.
Ten Senior All Stars met on Tuesday for card making and chair exercise.
On Wednesday, 39 Highland Village Senior All Stars went to the Choctaw Casino trip.
The Senior All Stars met at Zone Action Center for the Senior Putt-Putt league on Friday to play against the YMCA and Flower Mound senior groups.
HUMAN RESOURCES / STAFF TRAINING
Human Resources:
Fire:
Police
CITY MANAGER / CITY COUNCIL
On Friday I met with the Area Manager for ONCOR Electric Delivery. Danny Hodges wanted to inform us that the ONCOR transmission towers that run through Highland Village have been designated as the primary route for bringing the West Texas Wind Farms generated power into the Metroplex. The project will consist of installing additional power lines on the tower, which will be a multi-phase project with the ultimate completion of the project in 2012. Construction will begin in Highland Village within the next 6 to 9 months.