The weekly TXDOT FM 2499 project meeting was canceled this week. The project status is as follows: The contractor continues to perform concrete pours of the bridge spans on the north side of the lake water level for the Poindexter bridge. They will continue to pour concrete…
Read More »
Recap of City Issues - June 19, 2009
Posted on June 19, 2009
Scott Kriston attended the the weekly TXDOT FM 2499 project meeting. The project status is as follows: The contractor relocated to the north side of the lake water level for the Poindexter bridge and continues to perform concrete pours of the bridge spans. They will continue…
Read More »
Recap of City Issues - June 12, 2009
Posted on June 12, 2009
Scott Kriston attended the weekly TXDOT FM 2499 project meeting. The project status is as follows: The contractor finished the concrete pours on the Poindexter bridge south of the lake water level. The contractor will relocate to the north side of the lake water and continue to…
Read More »
Recap of City Issues - June 5, 2009
Posted on June 5, 2009
This week has been one of the most exciting times for myself, Mayor & Council, City Staff and for the residents of Highland Village with the acquisition of Doubletree Ranch by the Trust for Public Land. I would like to thank Niels Brown with the Trust for Public Land, if it was not for…